Proposal details
The abovementioned development application is being advertised for public comment and proposes the following:
- Movement and storage of up to 230,000m3 of material from Lot 9006 (adjoining to the West) to the subject site;
- Works envisaged to occur over a seven-week period from date of commencement;
- Sand scrapers already operating on Lot 9006 as part of the subdivision works will extract from Lot 9006 and transport to and deposit on lot 9005;
- Maximum of four sand scrapers will be used, and it will take approximately 325 movements a day to form the stockpile;
- Sand scraper movements to occur between the hours of 7:00am – 5:00pm Monday to Friday and 7.30am – 5.00pm on Saturday; and
- Movements will be between:
- Lot 9006 > Lot 9005.
To Comment
Submit your feedback using the form below, you can also attach additional documents (plan, diagrams, photographs etc).
For your feedback to be considered, you must provide your full contact details. This information will be treated as confidential and will not be published or linked to your comments in any public report on the outcomes of the consultation.
We will also keep you updated on the progress of this proposal.
Following the conclusion of the consultation period the application will then proceed to be determined by the City’s Administration.